Looking forward at the week ahead, we're anticipating a lot of work at tin box. Our erector should be able to finish installing the roof decking this week (we're still waiting on two pieces of steel that weren't shipped with the z-purlins). The exterior roof panels arrive Tuesday, and should start going up right away. Our panel manufacturer plans to begin fabricating the exterior wall panels Monday and deliver them to the site Friday.
Meanwhile, the neighbors clearly approve of the project...
Prefabrication must be an aphrodisiac for peafowl.